Environmental cleanup reaches milestones as work continues

The Seaplane Lagoon’s north side will be looking like its old self in a few months. The Navy has begun dismantling the waterproof concrete-walled containment system that was used for three years for dewatering and testing of soil dredged from the Seaplane Lagoon, marking a major cleanup milestone. Prior to that dredging work, much of the lagoon’s north frontage served as a staging area for replacement of storm drain lines contaminated with radium-226.

Construction of a new and improved soil cover over a waste disposal site concluded this spring, marking another milestone. The 110-acre site on the southwest corner of Alameda Point took 10 years of haggling about potential environmental impacts before a cleanup plan was adopted in 2010. Work began in early 2013. The dome-shaped soil cover required 500,000 cubic yards of barged-in soil to complete.

North Pond of West Wetland on southwest corner of Alameda Point.  Pond is connected to San Francisco Bay via a new culvert near upper left of pond.  Landfill soil cover is partially visible on far side of pond and will be seeded with flowering native grasses later this year.
North Pond of West Wetland on southwest corner of Alameda Point. Pond is connected to San Francisco Bay via a new culvert near upper left of pond. Landfill soil cover is partially visible on far side of pond and will be seeded with flowering native grasses later this year.

At the far northwestern corner of the Point, work is about to begin on another long studied and analyzed waste disposal site. In a few months, the Navy will be installing an interlocking steel retaining wall along 200 yards of the Bay shoreline to contain contaminated burned waste material that was bulldozed into the Bay more than a half century ago. Water dye tests showed no toxics are leaching into the Bay, but members of the Restoration Advisory Board (RAB) questioned whether the barrier would withstand a catastrophic earthquake. Partially covered by runway pavement, the entire 30-acre site will receive a three-foot soil cover. The work is expected to be completed in 2015. The area will be available for passive recreational use such as hiking trails when the city receives the land.

Northwest tip of Alameda Point where Site 1 is located.  Waste burning area is here.  Trees have been removed.  Port of Oakland is in background.
Northwest tip of Alameda Point where Site 1 is located. Waste burning area is here. Trees have been removed. Metal retaining wall will go here.  Port of Oakland is in background.

One of the longest-running and most problematic cleanup sites is at the old Naval Air Rework Facility (NARF), also known as Building 5, covering nearly one million square feet. Radium paint used for aircraft dial painting, and chemicals associated with engine repair work led to contamination that is still being remediated. The entire floor area will be scanned again for radiation in 2015, following up on at least three prior scanning surveys of walls, ceilings, pipes, and ducts. The year 2015 will also see the Navy returning to the site for a final round of groundwater cleanup treatments targeting contamination remaining after an intensive cleanup effort a decade ago.

Building 5, also known as Naval Air Rework Facility (NARF), where additional radium-226 and groundwater cleanup is planned.  At the corner of West Tower Avenue and Monarch Street.
Building 5, also known as Naval Air Rework Facility (NARF), where additional radium-226 and groundwater cleanup is planned. At the corner of West Tower Avenue and Monarch Street.

Next door to the Bladium Sports Club on West Tower Avenue, another previously treated groundwater cleanup site will be treated again. Workers have already begun boring holes in the pavement for a network of hoses that will be used for introducing contaminant-eating bacteria into groundwater along with a bacteria food source.

On Saturday, July 12, the Navy’s annual cleanup site tour visited four of the cleanup areas. The most impressive stop was the 110-acre landfill site mentioned above. For the first time in over 15 years, members of the public were allowed to walk around and enjoy the magnificent views from the embankment that is closer to San Francisco than to city hall. The fencing is all gone, and with it the radiological warning signs. The Navy replaced an aging metal culvert that connects the site’s North Pond to San Francisco Bay with a concrete culvert.

New culvert being installed connecting San Francisco Bay, which is to the right, and North Pond of the West Wetland at Alameda Point.  Navy photo taken 5/22/14.
New culvert being installed connecting San Francisco Bay, which is to the right, and North Pond of the West Wetland at Alameda Point. Navy photo taken 5/22/14.
New culvert being installed.  North Pond of West Wetland at Alameda Point in foreground, San Francisco Bay in background.  Navy photo.
New culvert being installed. North Pond of West Wetland at Alameda Point in foreground, San Francisco Bay in background. Navy photo.

Tour participants were able to see the area’s expanded wetland with a new tiny island. Caspian Terns started nesting on the island a few months ago, another type of milestone. “The last time Caspian Terns were seen in that area nesting was in 1999 when only one nest was detected,” said Alameda wildlife biologist and Alameda Point bird surveyor Leora Feeney. The 79-acre soil cover on the landfill will be seeded with flowering native grasses later this year. The vegetation mix was chosen by the RAB.

South Pond of West Wetland at Alameda Point.  Island in pond has become a nesting site for Caspian Terns.  Looking north toward Port of Oakland.
South Pond of West Wetland at Alameda Point. Island in pond has become a nesting site for Caspian Terns. Looking north toward Port of Oakland.

According to the Navy’s environmental cleanup coordinator, Derek Robinson, $513 million has been appropriated to date for Alameda Point cleanup, although some of it remains to be spent on upcoming work. His office, the Base Realignment and Closure Program, estimates another $80 million will be needed by the time remaining projects and follow-up monitoring are completed.

Later this year, the Navy is expected to transfer to the city the 33-acre North Housing site and seven-acre former Island High School site that sit next to Alameda Landing and Estuary Park, marking another milestone on the long and winding cleanup road to civilian use.

This story appeared in the Alameda Sun:  Print edition front page and online edition.

Navy Environmental Tour Guide July 12, 2014 – Cleanup Fact Sheets

Navy Presentation Environmental Cleanup Program Review July 12, 2014 to Restoration Advisory Board

More photos and a map

Caspian Terns and chicks at West Wetland, Alameda Point.
Caspian Terns and chicks at West Wetland, Alameda Point.  Click on image to enlarge.
Trail on embankment at southwest corner of Alameda Point.  Looking south with San Francisco Bay to the right and ahead.  Additional trail to the right at riprap elevation.
Trail on embankment at southwest corner of Alameda Point. Looking south with San Francisco Bay to the right and ahead. Additional trail to the right at riprap elevation.
Concrete pad served as a base for conveyor that transferred soil from barge to land for the soil cover at Site 2.  Contractor left it in place and added a few amenities for future users of a place they had come to appreciate the beauty of as they worked here for a year.  Thank you, TetraTech.
Concrete pad served as a base for conveyor that transferred soil from barge to land for the soil cover at Site 2. Contractor left it in place and added a few amenities for future users of a place they had come to appreciate the beauty of as they worked here for a year. Thank you, TetraTech.
Dredging the northwest corner of the Seaplane Lagoon at Alameda Point in February 2012.  Tarmac dewatering, drying, and testing area behind black tarp is now being dismantled.  All dredging work is completed.
Dredging the northwest corner of the Seaplane Lagoon at Alameda Point in February 2012. Tarmac dewatering, drying, and testing area behind black tarp is now being dismantled. All dredging work is completed.

Previous stories about waste disposal areas: 

Scenic Alameda Point wildlife refuge section to be off limits with security fence (May 31, 2012)

Update notes: Subsequent criticism of the Navy as to the necessity of a security fence by members of the public and regulatory agencies led to the removal of the security fence from the final work plan design. The Navy also agreed to shorten the soil gas vents to two feet, since only trace amounts of methane gas are now emitted from the landfill waste, most of which is industrial and did not produce methane in the first place.  Additionally, the Navy agreed to examine the aging metal culvert that connects the North Pond of the West Wetland to San Francisco Bay.  The culvert provides the water lifeline for the North Pond habitat and was at risk of collapse and being stopped up with debris.  The Navy replaced the metal culvert with a concrete culvert (see photo above) and debris screen.

Navy receives comments on landfill/wetlands plans on Alameda Point wildlife refuge (July 15, 2012)

Ending threat of solvents in groundwater leaching into San Francisco Bay (August 31, 2012)

Cleanup plan changes at waste burning area (April 5, 2013)

Landscaping the Navy’s underground waste disposal site (June 4, 2013)

Massive landscaping project changing scenic area on Nature Reserve (August 5, 2013)

Landfill landscaping on Nature Reserve – Update October 2013 (October 26, 2013)

Dragon boat, canoe races held at Alameda Point

Alameda Point’s Seaplane Lagoon was the site of two days of boat races on the weekend of July 12-13.  The two-day event was sponsored by the Northern California Outrigger Canoe Association and the California Dragon Boat Association.  Saturday was for the outriggers, and Sunday was for the dragon boats.

The Seaplane Lagoon was also the launch site on Sunday for outrigger canoes heading out to the tip of Alameda Point for a race to the San Leandro Marina.   The Alameda-Point-to-San-Leandro race was sponsored by Wave Chaser.

Here are some photos showing what a great venue the Seaplane Lagoon is for outdoor events like boating.  

Note that the temporary dock facility used by the boaters was installed by Artemis Racing when they began training out of Alameda Point for 2013 Americas Cup.    

Outrigger canoes Alameda Point
Outrigger canoe race on July 12, 2014 at Alameda Point’s Seaplane Lagoon.

Outrigger canoes at Alameda Point

Outrigger canoe team staging area

Outrigger canoe team banners at Alameda Point

Dragon boat race on July13, 2014 at Alameda Point's Seaplane Lagoon
Dragon boat race on July13, 2014 at Alameda Point’s Seaplane Lagoon

Dragon boats racing at Seaplane Lagoon, Alameda Point

Dragon boat team competing in race at Alameda Point's Seaplane Lagoon.
Dragon boat team competing in race at Alameda Point’s Seaplane Lagoon.
Dragon boat team heading to starting line.
Dragon boat team heading to starting line.
Dragon boat team returning to dock after race.
Dragon boat team returning to dock after race.

Dragon boat team huddle

Dragon boat team huddling at Seaplane Lagoon

Dragon boat team

Dragon boat team at Seaplane Lagoon, Alameda Point

Dragon boat team huddle

Dragon boat teams queuing up to board their boats for next race.
Dragon boat teams queuing up to board their boats for next race.

Dragon boat teams boarding their boats

Dragon boaters on Seaplane Lagoon boating dock

Dragon boaters returning to staging areas after race

Dragon boat "village" at Seaplane Lagoon, Alameda Point

Dragon boat "village"

Dragon boat "village" at Seaplane Lagoon

Dragon boat team

Dragon boat race spectators

Spectators at Seaplane Lagoon dragon boat races

All-female Wave Chaser team launching boat for race to San Leandro Marina.  Alameda Point Seaplane Lagoon.
All-female Wave Chaser team launching boat for race to San Leandro Marina. Alameda Point Seaplane Lagoon.

Female Wave Chasers heading to race

Wave Chasers headed to race starting line in SF Bay

Wave Chaser carrying boat to Seaplane Lagoon launch

Wave Chaser launching boat

Wave Chaser launching boat

Wetland park plan at Seaplane Lagoon gets a boost

It’s more likely a new wetland will be created on the western shoreline of the Seaplane Lagoon at Alameda Point, thanks to lobbying efforts led by the Sierra Club.

Sierra Club in Alameda's 4th of July Parade 2014
Sierra Club in Alameda’s 4th of July Parade 2014

On July 1, 2014, the Alameda City Council added language to the Alameda Point Town Center and Waterfront Specific Plan that raises the commitment to remove pavement from the western side of the Seaplane Lagoon for wetland—an area called De-Pave Park.  Lobbying efforts convinced the council to include the following options to help facilitate the wetland park creation:  1) creating a wetland mitigation bank; 2) adding the area to a possible national wildlife refuge on the federal property; and 3) working with local community members who may identify funding sources for creating the passive park area. Continue reading “Wetland park plan at Seaplane Lagoon gets a boost”

Ospreys nesting at Alameda Point interrupted again in 2014

In early June a pair of returning ospreys looked ready for the day in their newly made nest atop a parking lot light pole at Alameda Point, but they had no chicks to attend to. The pair’s first nest this season — on a nearby ship — had been removed during construction.  Their second attempt faced interference from another osprey.  By June, hopes for fledglings this year had faded.  An ad hoc group of osprey watchers is hoping a dedicated osprey platform can be erected at Alameda Point in a spot where competing interests and annoyances of daily commotion don’t intrude into the reproductive efforts of the ospreys.

Male osprey bringing nesting material to light pole near maritime ships at Alameda Point with female looking on.
Male osprey bringing nesting material to light pole near maritime ships at Alameda Point with female looking on.

In early March the osprey pair began building their first nest this year where they had nested last year — on a kingpost high atop the maritime ship Admiral Callaghan. The ship’s owner, the Maritime Administration (MARAD), had removed last year’s nest. This year MARAD moved quickly to stop the nest building to avoid potential delay to relocate a nest if ordered into service. “The Maritime Administration worked closely with the California Department of Fish and Wildlife on dismantling the nest and installing deterrence devices on March 19 prior to any eggs being laid,” said Alameda resident Harvey Wilson, who has been monitoring the ospreys at Alameda Point.

Crew removing osprey nesting material from kingpost on Admiral Callaghan maritime ship at Alameda Point, March 2014.
Crew removing osprey nesting material from kingpost on Admiral Callaghan maritime ship at Alameda Point, March 2014.  Photo by Harvey Wilson.

But that removal didn’t end the ospreys’ interest in the ship, at least not for the male osprey. He soon started bringing sticks to a lower-level hoisting post on the ship. The female, on the other hand, took a liking to a light pole in the parking lot next to the wharf. After weeks of back and forth episodes of mating and nest building at both sites, the female won, and nest building started ramping up on the light pole. At one point, it appeared that the female was hunkering down in the nest, a sign that eggs had been laid and incubation had started. But soon another female osprey appeared, trying to lure the male from his duties and disturbing the composure of the female.  

Female osprey bringing nesting material to nest on parking lot light pole near maritime ships at Alameda Point - May 2014.
Female osprey bringing nesting material to nest on parking lot light pole near maritime ships at Alameda Point – May 2014.

The third osprey now seems to have moved on, and the original pair has continued to visit the nest, but the lateness of the season offers little hope that eggs will be laid again, if they ever were, this year.

Osprey with striped bass in early June 2014 near maritime ships at Alameda Point.
Osprey with striped bass in early June 2014 near maritime ships at Alameda Point.

The appearance of ospreys at Alameda Point, first documented in 2010, is part of larger Bay Area phenomenon of ospreys beginning to nest on the shores of San Francisco Bay. Osprey first began nesting in the San Francisco Bay Area in the year 2000, having moved their nesting range further south. There are currently 24 active nests on San Francisco Bay. One theory for the ospreys’ Bayside nesting interest is a reduction of silt in the Bay, making it easier for osprey to catch fish, their primary food source. The high silt levels are a legacy of the gold mining era during which streambeds emptying into the Sacramento River were blasted with water canons to expose gold particles. Ospreys normally return to the same nest every year, but the Alameda Point pair has now used three different sites. In 2012 they successfully raised their lone chick on an old light stand on the western jetty of the Seaplane Lagoon, their regular nest for three years.   For unknown reasons, they chose the heights of a maritime ship in 2013, and in 2014 a parking lot light pole.

Osprey pair on their light pole nest April 18, 2014 as nest building continued.
Osprey pair on their light pole nest April 18, 2014 as nest building continued.

An ad hoc group of osprey watchers that includes members of the Golden Gate Audubon Society have been discussing with the city the possibility of erecting a permanent osprey nesting platform on the western side of the Seaplane Lagoon. “City staff has been and is willing to continue to work with interested members of the local community to potentially establish an osprey platform at Alameda Point,” said Jennifer Ott, Chief Operating Officer for Alameda Point.  “The identification of an appropriate location for this platform will depend on a number of factors, including approval by the United States Fish and Wildlife Service.” In March of this year, the city of Richmond’s Public Works Department assisted with the installation of an osprey platform at Pt. Molate, which helped divert nesting efforts from a utility pole with live wires. PG&E, with extensive raptor nesting diversion experience throughout California, has offered to install a pole and nesting tub at Alameda Point for free.

City of Richmond public works employee after installation of nesting tub at Pt. Molate.
City of Richmond public works employee after installation of nesting tub at Pt. Molate – March 2014.  This photo and three below are by Tony Brake.

“It is difficult to know what the ospreys feel or how they respond or what their capacity is for all the activity that goes on around them, but this season certainly challenged them,” said Alameda wildlife biologist Leora Feeney.  “Providing safe platforms for them out of busy corridors would serve everyone better.”

Female osprey arranging nesting material with male looking on.
Female osprey arranging nesting material with male looking on.

Published on the Golden Gate Audubon Society’s blog Golden Gate Birder.

See also:

Shoreline grassland, wetland: An opportunity now at Alameda Point

The city’s west side of the Seaplane Lagoon at Alameda Point is mostly pavement – acres of it – with a few old buildings abutting a wetland on the federal property. The city claims its long-range plan for this area features a conversion to a wetland habitat, but their only commitment is to continue leasing the buildings to generate revenue while allowing a sea of unnecessary pavement to remain as an environmental blight.

Seaplane Lagoon west side, looking south.  Seaplane Lagoon on left, Alameda Point Channel and SF Bay in background.
Seaplane Lagoon west side, looking south. Seaplane Lagoon on left, Alameda Point Channel and SF Bay in background.  Temporary fence to be removed by end of 2014.

Opportunities for implementing ecosystem enhancement, both short and long term, have yet to be explored for this area. We need to start moving in a direction now that benefits the environment by reducing climate impacts, improves the atmosphere around nearby businesses, adds to public enjoyment, and increases wildlife habitat.

Proposal for ecosystem enhancement

Short-term plan – Remove all pavement not required for commercial tenants. Recycle the pavement at the VA’s Alameda Point project site where they will be raising elevation and need base rock and fill. Once the pavement is removed and the soil exposed, native vegetation could be planted. Native vegetation will absorb CO2, produce oxygen, eliminate the heat island effect of the former pavement, add wildlife habitat, improve the aesthetic appearance of the property, and make it attractive as a hiking, jogging, and cycling destination.

          Step 1 – Set aside money from lease revenue generated on the west side of the Seaplane Lagoon for pavement removal and introduction of native plant vegetation.

          Step 2 – Explore recycling pavement at Alameda Point.

          Step 3 – Explore grant sources for conversion of paved areas to native vegetation, i.e., state air quality board, EPA, State Lands Commission, etc.

West side of Seaplane Lagoon, looking north.  Seaplane Lagoon on right.  Buildings 29 and 25 on left.  Most of this area could be covered with native grasses with no negative effects on commercial leasing.
West side of Seaplane Lagoon, looking north. Seaplane Lagoon on right. Buildings 29 and 25 on left. Most of this area could be covered with native grasses with no negative effects on commercial leasing.

Long-term plan – Establish an Alameda Point Wetland Mitigation Bank, which would incorporate the west Seaplane Lagoon acreage along with 50 acres on the northwest side of Alameda Point (Northwest Territories). Investment money would provide the capital for wetland creation, with money being recouped when mitigation credits are sold to developers elsewhere in the Bay watershed to offset their project’s impacts. As a general rule, a tidal wetland is worth at least as much as it would cost to create it. That’s why businesses exist that specialize in mitigation banks. In theory at least, the wetland project could be self-funding.

          Step 1 – Commission a study on wetland mitigation bank formation using lease revenue from Buildings 25 and 29.

Information about wetland mitigation banking:

Report To The Legislature – California Wetland Mitigation Banking – Jan. 2012 

U.S. Wetland Banking – Market Features and Rules

Forbes wetland article 4/25/2014 from BCDC

West side of Seaplane Lagoon looking south, with channel and Breakwater Island in background.
West side of Seaplane Lagoon looking south, with channel and Breakwater Island in background.
West side of Seaplane Lagoon, looking northeast from shoreline riprap, with lagoon and hangars in background.
West side of Seaplane Lagoon, looking northeast from shoreline riprap, with lagoon and hangars in background.  Pavement here will serve no commercial purpose under current low-impact guidelines.
Great Blue Heron gathering nesting material on western edge of Seaplane Lagoon for nearby nest.  Increased vegetation will bring more birds along shoreline.
Great Blue Heron gathering nesting material on western edge of Seaplane Lagoon for nearby nest. Increased vegetation will bring more birds along shoreline.
CA Least Terns engaged in courtship ritual of exchanging a fish on jetty adjacent to west side of Seaplane Lagoon - May 2014.
CA Least Terns (center of photo) engaged in courtship ritual of exchanging a fish on jetty adjacent to west side of Seaplane Lagoon – May 2014.
Barn Swallow on fence on west side of Seaplane Lagoon.  Common to the area, often seen flying low over the water looking for flying insects,  nesting almost exclusively on man-made structures, possibly Building 29.
Barn Swallow on fence on west side of Seaplane Lagoon. Common to the area, often seen flying low over the water looking for flying insects, nesting almost exclusively on man-made structures, possibly Building 29.
Breakwater Island viewed from shoreline on west side of Seaplane Lagoon.  Breakwater Island is a roosting site for CA Brown Pelicans and other birds.  Island owned by city of Alameda.
Breakwater Island viewed from shoreline on west side of Seaplane Lagoon. Breakwater Island is a roosting site for CA Brown Pelicans and other birds. Island owned by city of Alameda.
Landscape plan from 2013 showing no buildings on west (left) side of Seaplane Lagoon.  Buildings are now being recommended to stay.  Floating wetlands are a very long-range option if funding is available.
Landscape plan from 2013 showing no buildings on west (left) side of Seaplane Lagoon. Buildings are now being recommended to stay. Floating wetlands are a very long-range option if funding is available.
2014 plans for west side of Seaplane Lagoon show buildings in dashed lines.  Active leasing of buildings currently underway suggests buildings should be in solid lines and wetland in gray.
2014 plans for west side of Seaplane Lagoon show buildings in dashed lines. Active leasing of buildings currently underway suggests buildings should be in solid lines and wetland in gray.
Looking west from west side of Seaplane Lagoon.  Bay/Channel on left.  Building 29 on right.  City property extends beyond fence to far edge of Building 29 property line.
Looking west from west side of Seaplane Lagoon. Bay/Channel on left. Building 29 on right. City property extends beyond fence to far edge of Building 29 property line.
Runway Wetland area on federal property adjacent to Building s 25 and 29 on city property at west side of Seaplane Lagoon.  A naturalized west shoreline of Seaplane Lagoon, with public access, would enhance the greater wildlife habitat in this area.
Runway Wetland area on federal property adjacent to Buildings 25 and 29 on city property at west side of Seaplane Lagoon. A naturalized west shoreline of Seaplane Lagoon, with public access, would enhance the greater wildlife habitat in this area.

Take the plunge!  Remove pavement on the west side of the Seaplane Lagoon and improve our environment.

Gosling ready to plunge onto rocks below, on west side of Seaplane Lagoon, to get to parents in the Alameda Point Channel.
Gosling ready to plunge onto rocks below, on west side of Seaplane Lagoon, to get to parents in the Alameda Point Channel.  It was successful.

Black-crowned Night Heron Juvenile – Gallery and Video – Spring 2014

A Black-crowned Night Heron adult and its juvenile offspring were spotted along the south shoreline of Alameda Point during May and June of this year.  The juvenile was seen foraging for food on the shoreline, as well as using the old dock for a resting area.  Use of the old dock by a wide variety of birds, as well as a family of harbor seals, illustrates the habitat value of the waterfront and the wisdom of providing a new wildlife water platform when the Water Emergency Transit Authority removes the old dock for their new maintenance facility this year.

Black-crowned Night Heron juvenile and left and adult on right.  Perched on remnants of old Navy recreational dock in Alameda Point's Inner Harbor on south side.
Black-crowned Night Heron juvenile and left and adult on right. Perched on remnants of old Navy recreational dock in Alameda Point’s Inner Harbor on south side.
Black-crowned Night Heron juvenile foraging on Alameda Point shoreline.
Black-crowned Night Heron juvenile foraging on Alameda Point shoreline.

Black-crowned Night Heron juvenile Alameda Point

Black-crowned Night Heron juvenile June 2014

Black-crowned Night Heron juvenile close-up

Black-crowned Nigh Heron juvenile hanging out on dock with other wildlife.
Black-crowned Nigh Heron juvenile hanging out on dock with other wildlife.
Shoreline area where Black-crowned Night Heron juvenile and adult were viewed next to old dock at blue arrow.
Shoreline area where Black-crowned Night Heron juvenile and adult were viewed next to old dock at blue arrow.  Part of old dock in image has sunk.